County says 9-1-1 center about half complete; committee approves small change order and system contracts

5402181 ยท June 2, 2025

Get AI-powered insights, summaries, and transcripts

Subscribe
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

County staff reported the 9-1-1 center is about 50% complete and remains on schedule for a mid-September finish; the committee approved a $6,200 electrical change order and authorized vendor agreements for door access and fire alarm systems discussed during construction walk-throughs.

Columbia County staff reported that the new 9-1-1 call center project is approximately 50% complete and remains on schedule for a mid-September finish, which would allow a move and a brief operational transition ahead of an anticipated October start of service.

Staff said general contractors have completed rough HVAC, plumbing and electrical work and that a recent inspection with the town code officer raised no issues. The county requested and the committee approved a change order of $6,200 to add electrical outlets, data drops and monitor locations identified in walkthroughs with 9-1-1 staff.

Committee members also authorized the county to enter into agreements for the building access and alarm systems. County staff discussed procurement of a card access system from the vendor used by the county and a fire alarm contract with a vendor that currently services the county's fire training center; during the meeting staff referenced figures in discussion (door access and fire alarm line items were discussed around $63,000 each during the presentation). Staff said taking those systems out of the original construction contract and placing them with specialized vendors will save approximately $35,000 compared with the original single-contractor scope.

Project timeline and bidding: staff said bids for related projects (11 Warren, 610 building) are being coordinated; bid openings and pre-bid meetings were discussed for the Lehi/11 Warren project with dates provided for contractors. Staff said 30 contractors had picked up bid documents for the 9-1-1 center and that construction start is scheduled for September, noting some firms prefer not to begin during the school construction season.

Discussion and next steps: staff will continue to manage close coordination with contractors and vendors; the committee approved the change order and authorized vendor agreements to keep the project on schedule.