Board approves $282,066.68 pay estimate for Abel Stormwater lift station rehabilitation
Summary
The Board of Public Works approved pay estimate No. 1 for Abel Stormwater Lift Station Rehabilitation with Earth Incorporated following review by Strand construction management and Andy Constant.
Get email alerts on the Stormwater Pumping Stations topic
No spam. Unsubscribe anytime.
The Board of Public Works approved pay estimate No. 1 for the Abel Stormwater Lift Station Rehabilitation contract with Earth Incorporated, in the amount of $282,066.68.
A staff member stated the project had been reviewed and approved by Strand, the construction management firm, and referenced Andy Constant in that context. The staff member recommended approval of “P. S. Number 1 of $282,066.68.” A board member moved to approve the pay estimate; another member seconded and the board voted in favor.
The transcript records the review by Strand and the dollar amount but does not include a breakdown of work included in the pay estimate or the remaining contract balance. The board recorded the approval by voice vote and no opposition was recorded.