Board approves $282,066.68 pay estimate for Abel Stormwater lift station rehabilitation

5400520 · July 15, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Board of Public Works approved pay estimate No. 1 for Abel Stormwater Lift Station Rehabilitation with Earth Incorporated following review by Strand construction management and Andy Constant.

The Board of Public Works approved pay estimate No. 1 for the Abel Stormwater Lift Station Rehabilitation contract with Earth Incorporated, in the amount of $282,066.68.

A staff member stated the project had been reviewed and approved by Strand, the construction management firm, and referenced Andy Constant in that context. The staff member recommended approval of “P. S. Number 1 of $282,066.68.” A board member moved to approve the pay estimate; another member seconded and the board voted in favor.

The transcript records the review by Strand and the dollar amount but does not include a breakdown of work included in the pay estimate or the remaining contract balance. The board recorded the approval by voice vote and no opposition was recorded.