Council awards up to $2.2M contract to Webb Construction for permanent police evidence facility

5398287 · July 15, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The committee approved a contract not to exceed $2.2 million to Webb Construction to design and build a 10,500-square-foot permanent police evidence facility at the public safety campus, with a $220,000 contingency. Staff said design work has already begun and construction is expected to be completed by Dec. 31, 2025.

The City of Roswell’s committee on July 15 approved awarding a contract to Webb Construction for design and construction of a permanent police evidence facility at the public safety headquarters, with a contract cap of $2,200,000 and a $220,000 construction contingency.

Brian Watson, public works director, told the committee the project will produce a 10,500-square-foot multiuse facility on the northern portion of the new public safety headquarters at 1080 Holcomb Bridge Road. Watson said the building will include permanent evidence storage, a motor barn and a CrossFit gym for public safety staff, and that the contract covers both building design and construction.

Watson said design work “actually already started” and gave an expected construction completion timeline: “the construction would be completed by the end of the year.” Committee members also discussed the logistical effort of relocating current evidence holdings from the facility across the street to the new building.

The committee voted to award the contract (motion by Councilmember Gee Lee Hills; second by Councilmember Visa). The motion passed unanimously. Watson said staff also recommends a $220,000 contingency to cover unforeseen circumstances during construction.

Nut graf: The award commits city funds to a permanent evidence and operations building intended to consolidate evidence storage and related police support functions at the public safety campus. Staff presented timing and logistics considerations and said the design phase is underway; the committee approved the contract and contingency to move the project forward.

Details and next steps Staff recommended Webb Construction based on experience designing and constructing similar facilities for military and private clients. Watson said the current evidence operation across the street will be moved into the new facility once construction is complete; he described the move as a substantial undertaking.

Mayor Kurt Wilson and council members expressed support for the project. After the vote, staff will finalize the contract, continue design work already in progress, and proceed to construction with the stated goal of completing the facility by Dec. 31, 2025.