Pales Park approves $206,496 pay estimate for water‑main relocation tied to IDOT culvert work

5398193 · July 14, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved pay estimate No. 1 to Ares Construction for the water‑main relocation required so IDOT can reconstruct two box culverts that carry Mill Creek; council recorded contract adjustments and praised the contractor's speed.

The Pales Park Village Council on July 14 approved pay estimate number one for the Hundred and 20 Third Street water‑main relocation, awarding payment to Ares Construction Incorporated for work needed so the Illinois Department of Transportation can reconstruct two box culverts carrying Mill Creek.

Public Works reported Ares submitted invoice number 1 for $206,496.90 and recommended payment. Council materials listed the original contract sum as $589,132 and identified change orders totaling $10,659, which increase the contract to $599,791. The council approved the payment by motion.

Mayor Milovich Walters said, “in a little over a week, Ares was able to lower the water main on 1 side of the street already, allowing us to move to the other side of the street near Elm now.” The mayor added that once the village work is finished, IDOT will build wing walls and related structures to support the box culvert.

Commissioner Patan moved to approve invoice number one for the Ares Construction relocation project in the amount stated on the invoice; a colleague seconded the motion. A roll call vote followed with all members voting yes.

Public works noted the village’s portion will be finished after Ares lowers the water main on the remaining side of the street; no additional schedule or final completion date was provided in the meeting record.