Construction update: STEM lab, music and band additions on track but parking and fiber issues could add cost
Summary
Jason Erb of SiteLogic told the board key additions — the STEM lab, music room and middle‑school band room — are progressing and remain on schedule for occupancy before the 2025 school year, but site discoveries on an existing parking lot and unresolved fiber relocation could increase costs.
Jason Erb, a SiteLogic representative, gave a multi‑facility construction update, saying the STEM lab, music room addition and middle‑school band room are substantially complete and that the overall project is "on schedule, on schedule, ish," though a handful of site issues could affect contingency spending and certain turnovers.
Progress and schedule: Erb said window frames, roofing and many interior finishes are in place on the STEM lab and related additions, casework and countertops are being installed, and ceilings and HVAC work are moving toward completion. He said the STEM lab had been running roughly 11 days behind the original schedule but contractors and SiteLogic do not anticipate missing the 2025‑school‑year turnover for most additions.
Parking and pavement discovery: exploratory work…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat