City administrator reports DEQ permit for industrial-park sewer and progress on Miller Street and 502 South Wilson projects
Summary
Administrator Bridal Prince told the council the REAP 2024 industrial-park project now has DEQ-approved sanitary sewer plans and permit; Miller Street work is underway with undercutting and gravel in place; at 502 South Wilson HVAC installation and fence removal work are in progress.
Bridal Prince, the city administrator, told the Bonita City Council on July 15, 2025, that the city received DEQ-approved plans and a permit for the sanitary sewer portion of the REAP 2024 project at the industrial park and that work on that project will begin. Prince also reported progress on Miller Street, saying roads have been undercut,…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat