PACE Center renovation advances; fire-suppression mobilization eyed for fall
Summary
Facilities staff reported punch-list completion at the PACE (bridal) building, skylight removals, insulation and upcoming fire-suppression work; staff estimated full system functionality by December and said pre-K classroom slab pours and finishes are under way.
Get email alerts on the Pace Center Renovation topic
No spam. Unsubscribe anytime.
Facilities staff updated the subcommittee on July 14 about ongoing work at the PACE Center (the former bridal building), including final punch-list items, skylight removals, roof work and the next major phase: upgraded fire suppression for auditorium and other spaces.
Why this matters: the PACE Center is being adapted to host pre-K classrooms and district offices; the extent and scheduling of fire-suppression upgrades determine when interior construction and classrooms can be completed and occupied.
Work completed and remaining
Mr. Pacheco reported that roofing punch-list items are finished, skylights were removed permanently to eliminate leakage, and the new roof meets current insulation code. He said the contractor will soon mobilize to install an upgraded fire-suppression system — a complicated task because the auditorium requires a system protecting a large volume above ceiling while the seating area below must be protected differently. Pacheco said he expects fire-suppression work to start soon and that a fully operational system could stretch into December.
Other construction activity
Pacheco said crews are removing old block wood flooring where required, pouring slabs and preparing back areas for pre-K classrooms; the district is staging classroom furniture and supplies to support that work. He said water-service capacity is adequate but a pressure pump will be required to meet suppression demands; that work does not require a new service trench.
No formal action
This was an informational update; no motions or votes were taken. Committee members thanked staff and praised the visible improvements at other recent projects.
Quotes
“I went to the Wharton School… and I remember the condition of that building before you and your crew got your hands on it… it looks absolutely beautiful,” committee member Mr. Corey said, praising recent renovations. Mr. Pacheco said, “I'm gonna guess that we'll be pushing December, to have a complete system and operational.”
Ending
Staff will continue work and coordinate mobilization of fire-suppression contractors; committee members asked for a schedule and the funding sources for the remaining work to be provided to the full committee.