Council approves $2.20 million change order to start Santaquin library interior work

5393385 · July 16, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved Guarantee Maximum Price (GMP) change order No. 3 for $2,199,788 to contractor Ellsworth Paulson for the library interior; furniture, fixtures and equipment (FF&E) and staffing are not included and will require separate funding.

Santaquin City Council approved a Guaranteed Maximum Price (GMP) change order July 15 in the amount of $2,199,788 to Ellsworth Paulson to complete the interior construction of the city library in the west wing of City Hall.

City staff noted the approved work covers construction only; the change order does not include FF&E (furniture, fixtures and equipment) — shelving, seating, tables and other library furnishings — which staff estimated could add roughly another $500,000 or more and will require separate fundraising or budget allocation. The mayor reported about $118,000 in private donations has been received to date with over $100,000 pledged but not yet collected.

The contractor plans to begin on-site construction the first full week in August, shortly after the city’s Orchard Days celebration; staff estimated the interior construction schedule at roughly eight to 12 months depending on equipment lead times (elevators and specialty items).

Councilmember Travis moved to approve GMP change order No. 3 and the motion passed on a recorded vote (ayes recorded). The council and staff said the next steps will be to finalize the budget allocations for construction, continue private fundraising for FF&E, and later present staffing and operating-cost implications for the expanded library footprint.

Ending: With the change order approved, construction mobilization will begin in early August; the city will return to council with FF&E and staffing proposals as funding becomes available.