Causeway south boat ramp project delayed to early 2027; city to seek temporary measures to open an additional gangway

5393191 · July 16, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City staff told the council that lead times for floating docks and gangways pushed the Causeway south ramp construction into first quarter 2027; staff said it will keep looking for temporary floating solutions to open at least one gangway during the coming boating season.

City staff updated the City Council that the Causeway south boat ramp project will be delayed because lead times for manufactured floating docks and gangways are longer than expected. After contractor pre‑construction meetings staff learned the docks and gangways will take roughly six months to fabricate and deliver, which pushed the recommended start of construction to the first quarter of 2027.

City Manager Wayne said the estimate from the contractor changed the start timeline: rather than beginning in August and working through the summer, staff recommended waiting until components arrive so the contractor does not start and then have to demobilize while waiting on long‑lead items. Staff also said their pre‑construction estimate of a total nine‑ to twelve‑month timeline has likely shortened to six‑to‑nine months once components are on site.

Temporary access and safety

Council members asked whether there is a current safety issue at the ramps. Staff replied there was not a known immediate safety hazard but acknowledged that restricted gangway access slows launches and can create bottlenecks; staff said they will keep searching for temporary gangways or floating solutions that could open an additional gangway for public use while the permanent docks are fabricated and delivered.

Ending note: Staff will return with any temporary solution options and with a revised construction schedule when manufacturers confirm delivery dates.