Council approves $35,807 change order for Burrell‑Holden Park; final project cost remains under budget
Summary
Council approved a $35,807.25 change order for Burrell‑Holden Park largely to cover additional siding, bringing the final contract with Amerson and Associates to $2,036,005.34—below the original $2.5 million construction budget.
Get email alerts on the Park Construction Change Order topic
No spam. Unsubscribe anytime.
The governing body approved change order No. 1 with Amerson and Associates for Burrell‑Holden Park, increasing the contract by $35,807.25 and producing a final contract total of $2,036,005.34. Staff said the overage was primarily for additional siding at the park.
Staff reported the original awarded contract was $2,000,726.97; the final total after the change order is $2,036,005.34. The project’s original construction budget was $2.5 million, so the project remains under the original budgeted amount, staff said.
The council voted to approve the change order at the meeting. No further modifications or additional funding requests were presented during the discussion.