Central Valley construction: monthly expenditures, change orders and schedule targets
Summary
Executive Program Director Gary Walker reported May construction activity for construction packages 1–4, including expenditures, change orders for utility conflicts, right‑of‑way progress and railhead milestones, and provided target dates for track, maintenance facility and station work.
Dr. Gary Walker, executive program director for the Central Valley segment, told the Finance and Audit Committee the program recorded about $62 million in total expenditures for May 2025 and provided monthly progress metrics for construction packages (CP) 1 and 2/3.
Walker said CPs showed change orders totaling about $13.3 million in May — including a notable CP‑1 change for Monterey Street in Fresno tied to conflicts with existing water and sewer utilities — and that risk contingency is at 7.1 percent, down…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat