Authority reports railhead progress; plans advance procurement of rail, ties, ballast and fiber for early track work
Summary
Staff said a Wascos-area railhead is on track, with about 1.25 miles of track installed and civil work completed; the authority plans separate commodity procurements and a multiple-award task-order contract (MATOC) to accelerate small-business participation.
Get email alerts on the Construction And Procurement topic
No spam. Unsubscribe anytime.
Authority staff reported the railhead project, the storage and staging facility intended to receive track materials, is on schedule and that civil work was completed in May. Bassem Aldem, the statewide regional director, said the railhead sits on roughly 150 acres the authority owns and includes about 10 miles of siding and storage track. He said approximately 1.25 miles of track had been placed as of early July and that the site's civil work was finished two months earlier. Staff said the authority is coordinating with BNSF for the railhead work and that the railhead will be used to receive commoditized materials such as rail, concrete ties, ballast, overhead contact system poles and wire, and fiber-optic cable. Emily Morrison, chief of contract administration, said the authority will bring separate solicitations for these commoditized items starting in August and that agreements will include pricing and escalation terms to limit later cost shocks. Morrison also described a five-year multiple-award task-order contract (MATOC) program meant to fast-track small and local contractors for construction work such as fencing, concrete pads and utility relocation tasks. The MATOC will be structured in separate pools (northern, southern, large business and utility relocation) to encourage local small-business participation and to limit geographic burdens on small firms. Task orders will be awarded based on qualifications with price negotiated at the task-order level, Morrison said; task-order ceilings were described as commonly $15 million but bonding requirements will be enforced at the task-order level rather than held collectively. Staff said the goal is to have commodities on site by Q2 2026 and to begin the bulk of track-laying work thereafter. The CEO told the board the authority aims to remove civil-work obstacles to track-laying by the end of 2026 so that heavy track work can proceed as planned.