Dunn County and State crews outline summer resurfacing, bridge sealing and localized closures
Summary
State and county transportation staff gave timelines and traffic-control plans for multiple resurfacing, overlay and bridge-deck projects across Dunn County, with some lane closures, flagging operations and local detours running through late summer and early fall.
State and county transportation staff reported a series of resurfacing and bridge maintenance projects that will require periodic lane closures, detours and local traffic control through mid- to late 2025.
Transportation staff said the state’s Highway 12 resurfacing between Highway 94 and Highway 25 will include a 1.75-inch mill and a 3.25-inch overlay; work will occur while crews close the west leg of Highway 12 with flagging operations in place. The Highway 64 project from County 0 to County W is planned as a 2-inch hot in-place recycle followed by a seal coat and fog seal; an engineer on the call said the contractor indicated that work could start as early as July…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat