Dunn County and State crews outline summer resurfacing, bridge sealing and localized closures

5375118 · July 11, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

State and county transportation staff gave timelines and traffic-control plans for multiple resurfacing, overlay and bridge-deck projects across Dunn County, with some lane closures, flagging operations and local detours running through late summer and early fall.

State and county transportation staff reported a series of resurfacing and bridge maintenance projects that will require periodic lane closures, detours and local traffic control through mid- to late 2025.

Transportation staff said the state’s Highway 12 resurfacing between Highway 94 and Highway 25 will include a 1.75-inch mill and a 3.25-inch overlay; work will occur while crews close the west leg of Highway 12 with flagging operations in place. The Highway 64 project from County 0 to County W is planned as a 2-inch hot in-place recycle followed by a seal coat and fog seal; an engineer on the call said the contractor indicated that work could start as early as July 14 and should finish by mid to late September. Bridge-deck sealing contracts — described as a three‑year maintenance cycle — are being performed as nightly off‑peak lane closures; the presenter said crews started June 5 near Osseo and expect to be working on bridges in Dunn County within the next week or two.

On county-maintained roads, the highway department reported completed paving on County Road S (170 to County Road N, town of Tainter) and County Road G (Highway D to State Highway 25, town of Tainter), with remaining shoulder work and pavement marking expected in the coming weeks. County Road A (Menomonie city limits south toward 10th Avenue) has had paving started this week, with a second mat scheduled; staff estimated completion, including shoulders and cleanup, in roughly three weeks. The Irvington Hill portion of County Road D has curb and gutter under construction and paving expected to start in the next two weeks, with an early-July completion target. A bridge replacement on County Road V north of Highway 64 was described as planned for later in the year; no firm start date was given and the road will be closed for the duration of that project.

Staff said temporary detours and local lane restrictions will be in place for several projects. For one state project, drivers were asked to use Oak Avenue as a detour; for others, periodic flagging and off‑peak closures are planned. County crews and the sheriff’s office have coordinated traffic control for zones where through traffic is prohibited, and county staff asked residents to avoid construction areas and obey posted signs.

Why it matters: the described projects affect travel on several county corridors and state highways during the summer and early fall; some closures and flagging operations will change traffic patterns, and county officials said they will post schedules and maps online.

As of the meeting, no motions or formal votes were taken on these items; staff announcements and planned operational coordination were the primary actions.