Committee endorses staff list for additional 2025 asphalt overlay, swaps two streets by consensus

5367307 · July 11, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Infrastructure and Facilities committee reviewed a staff list for additional 2025 asphalt overlay work and, by consensus, recommended substituting Quan and Knox streets for Woodland Ridge to address more urgent pavement failures.

City staff outlined additional streets proposed for asphalt overlay in 2025 using an extra $250,000 reallocated from winter maintenance. Public Works staff presented a spreadsheet of candidate streets, estimated material costs and milling needs.

Engineering and Department of Public Works representatives said the list prioritized streets where pavement structure and curb/gutter conditions make mill-and-overlay the best preservation method, and they noted lead‑service‑line replacement schedules affect timing because the city prefers not to overlay streets scheduled for imminent water‑service work.

Several alderpersons urged swapping Woodland Ridge (ranked in staff scoring as a 5) for Qua Street and Knox Street because those streets show more severe distress. After discussion, the committee signaled consensus to move Qua and Knox into the funded list in place of Woodland Ridge so the additional $250,000 of asphalt materials and available milling dollars would cover the revised list.

What happens next: Public Works will proceed to procure materials and bid milling/pulverizing work, and staff said the selected streets will be scheduled for paving during the 2025 construction season.