Court approves $351,700 amendment for Chambers Parkway design after pipeline conflicts force phase split
Summary
Commissioners approved a $351,700 amendment related to the Chambers Parkway project that added survey and project management work after the road design was split into two phases to avoid multiple pipeline conflicts; staff said the redesign reduced a potential $15 million pipeline relocation cost.
Chambers County Commissioners approved a $351,700 member request amendment for the Chambers Parkway Project to cover additional survey work and project management necessitated by splitting the project into two phases.
County staff said the original plan scoped a full design through to Needle Point and included a canal crossing, but staff split the work into Phase 1 (to the new soccer complex) and Phase 2 (from the soccer complex to Point Road) to avoid multiple pipeline conflicts along the corridor. Staff said the phased approach…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat