Board updates: AMCO awarded ROD bid; junior-senior high and elementary projects move toward bidding
Summary
Trustee Cooney reported that AMCO Enterprises won the ROD grant bid for the junior-senior high school project and summed budget figures for current and upcoming capital projects; the board reviewed budgets and upcoming bid walkthroughs.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Trustee Cooney reported on buildings and grounds projects at the May 14 meeting, saying AMCO Enterprises was awarded the ROD grant contract on April 30 for the junior-senior high school project. The winning base bid was $1,711,000; the board selected alternate option 1 (an upgraded cafeteria light package) for an additional $33,000, bringing the total award for that project to $1,744,000.
Cooney told the board the Fund 30 budget allocation for the project was $2,690,000, leaving an estimated unexpended balance of $947,000 that could be reallocated to another district project or returned to capital reserve at year-end audit. Projects for Grant and Roosevelt elementary schools will go to bid shortly; Grant is budgeted at $595,060 and Roosevelt at $347,060.
The junior-senior academic wing roof replacement was also scheduled to go out to bid with a budgeted construction amount of $1,756,000 and architectural costs estimated at $156,000. Cooney noted a bid walkthrough was scheduled for the next day, and the next Buildings & Grounds meeting was set for June 9.
The report was informational; the transcript indicates the AMCO award had already been made at an earlier April 30 meeting. Board members and committees are monitoring budget fits for the upcoming Roosevelt and Grant bids and will review options for the unexpended balance at audit or reallocation discussions.
No new appropriation or final contract award was moved at the May 14 meeting; Cooney’s remarks summarized the status of the projects, bid schedule and budgetary positions.