Keller Sports Park work 73% complete; full park construction expected to finish in January
Summary
Parks staff reported the sports park is 73% complete, with paving and sod installed on multiple fields, the equestrian restroom awaiting final inspection and a certificate of occupancy, and several original baseball fields scheduled for conversion to synthetic turf and offline through spring.
A parks staff member told the Keller Park & Recreation Board on July 3 that Keller Sports Park is about 73% complete and on track for major milestones this winter.
The parks staff member said paving and striping are finished for the soccer parking lot, the soccer parkway and the equestrian lot, and that new baseball fields have backstops, sod and synthetic turf in place. “Keller Sports Park, we’re 73% complete,” the staff member said. He added that the equestrian restroom/storage building is awaiting a TAS inspection and that the city expects to receive a certificate of occupancy and open that facility this month.
Why it matters: the construction timeline affects when youth and adult sports groups can use new…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat