MEDC hears contractor estimates doubling for McAllen wayfinding; staff to seek line-item breakdown and bid comparisons
Summary
Contractor estimates for the McAllen wayfinding and a downtown streetscape came back far higher than earlier planning numbers. Staff will request detailed cost breakdowns, explore phased work and consider additional bidding channels.
Get email alerts on the Infrastructure Projects topic
No spam. Unsubscribe anytime.
Tilly, a city staff member working on the McAllen wayfinding and streetscape project, told the Montgomery Economic Development Corporation the contractor-provided fabrication and installation estimate for wayfinding signage is between $1.5 million and $2 million, far higher than earlier estimates the board received.
The discrepancy prompted directors to ask staff to obtain a detailed line-item breakdown and to seek additional contractors or pricing sources. Tilly said the contractor’s estimate includes fabrication and installation and that some line items — particularly large entrance signs — appear to drive much of the cost. She suggested the board could reduce scope (for example omitting some entryway signs) or phase the work to lower near-term costs.
Staff also presented a consolidated streetscape proposal with a total cost shown in the contractor estimate of about $2,115,150, which they described as broken down into $1,785,150 for streetscape construction and engineering, $150,000 for drainage construction and engineering, $175,000 for water construction and engineering, and $45,000 for construction-phase services. Tilly and other staff explained those figures include paving, storm drainage and other civil work; board members asked whether the contractor used Sourcewell/government pricing and whether that affects comparability between bids.
Directors discussed schedule and approvals. Staff proposed bidding and starting construction after the holiday season, seeking a January start to avoid peak business-season disruption. Approvals will require property-owner buy-in, Planning & Zoning/PNC approval and city council action; staff said agreements and permits will need to be drafted if the board proceeds.
The board directed staff to: request a detailed, line-by-line cost breakdown from the contractor; check Sourcewell pricing and whether more competitive bids are available; and report back with options for phasing, scope reduction or alternate materials. No formal contract award or commitment was made during the workshop.