Select Board hears updates on double‑pole removals, Eust Middle School ownership and facilities work
Summary
Board heard a progress report on utility double‑pole removals, confirmed town ownership of Eust Middle School as of July 1, and discussed related facilities and energy items including job postings and a review of a long-standing power purchase agreement.
Get email alerts on the Municipal Operations topic
No spam. Unsubscribe anytime.
The Select Board on Monday received multiple operations updates: progress on utility double‑pole removals, confirmation that the town took ownership of Eust Middle School on July 1, and related facilities and energy-management items.
Why it matters: Removing double poles improves street safety and reduces clutter; ownership of the former Eust Middle School has immediate facilities-management implications including hiring and capital planning.
Double poles: A board member reported that National Grid initially identified roughly 80 double poles; after coordination and state engagement, 45 have been removed and the town now accounts for about 35 remaining poles. The town and utility representatives are compiling a list of remaining poles, owners, and removal timelines; town staff said some removals remain contingent on other carriers (Charter, Verizon) transferring or removing attachments.
Eust Middle School and facilities: Town staff confirmed the town became owner of the Eust Middle School property on July 1, 2025. The administration has posted job advertisements for a facilities manager (or part‑time facilities position), a part‑time town accounts position, and a full‑time principal assessor. Staff said the MVP (Municipal Vulnerability Preparedness) project reimbursement cycle closed and reimbursements were submitted to the state.
Energy and procurement: The town will review a long-standing power purchase agreement, and staff asked whether the town should invite the energy vendor to report on contract status and value given rising energy costs and planned occupancy/use of Thornton Burgess and other town properties. The board also discussed progress on a municipal network upgrade proposal from Charter and planned a kickoff with the regional energy manager.
Next steps: Town staff will continue to press utility partners on remaining double‑pole removals, proceed with recruitment for facilities and assessor positions, and schedule a follow-up to review energy agreements and Charter’s network-upgrade proposal.