Summary
The DuPage County Board approved a package of contract awards, contract amendments, intergovernmental agreement changes and funding appropriations during its meeting, including several weatherization and facilities contracts and a $7,072,090 contract for Rockwell automatic hardware and software support.
Get email alerts on the Procurement Contracts topic
No spam. Unsubscribe anytime.
The DuPage County Board on June 1 approved a series of awarding resolutions, contract amendments and budget adjustments covering weatherization services, facilities maintenance, public‑works projects, IT support and intergovernmental highway work.
The package included multiple weatherization and HVAC contracts for the July 1, 2025–June 30, 2026 program year: awarding resolutions to Arcos Environmental Services Inc. (HSP 28‑25) for mechanical/HVAC/weatherization labor and materials — contract not to exceed $135,000; Chicago United Industries Limited (HSP 29‑25) to furnish, deliver and install ENERGY STAR appliances — contract not to exceed $238,000; Healthy Air Heating and Airing (HSP 30‑25) for mechanical/architectural weatherization labor and materials — contract not to exceed $135,000; and My Greenhouse HVAC LLC (HSP 31‑25) for similar weatherization services — contract not to exceed $135,000. Each of those motions was moved and seconded by board members and carried after voice votes.
Facilities and public‑works items approved included: - A rescission of Requisition 25‑11‑86 for Sanders Distribution Air Care Services (re: kitchen duct and hood cleaning) and replacement with a new procurement for judicial facilities and the JTK administration building (contract to Airway Systems, F&P 33‑25) for July 9, 2025–July 8, 2027, not to exceed $37,525. - A renewal/award to Fox Valley Fire and Safety Company for preventive maintenance, testing and repair of fire and life‑safety systems (F&P 34‑25), third and final renewal option, not to exceed $117,250 for August 28, 2025–August 27, 2026. - A rehabilitation contract for a 250,000‑gallon elevated water storage tank to Dynamic Industrial Services (FWP 17‑25), not to exceed $390,600. - A purchase to Mid America Waters (FWP 18‑25) for hydrants and related materials, not to exceed $62,500 (first of three renewal options).
The board approved a large three‑year technology/industrial purchase order (PWP 19‑25) issued to Riviera Electric Supply Company to furnish Rockwell automatic hardware and software support for public works and stormwater management for May 29, 2025–May 28, 2028, for a contract total not to exceed $7,072,090. During discussion Vice Chair [Kozewski] was noted absent; a board member asked why the contract start date (May 29) had already passed. Valerie from procurement explained the contract started so there would be no service gap and that the contractor had not yet been required to provide services; she said a departmental decision would be needed if the board voted no and the contractor had already been used for amounts under $15,000.
Other transportation and public‑works motions carried included an amendment to an intergovernmental agreement with the City of Darien to replace a retaining wall along County Highway 31 (Plainfield Road) and increase county funding by $264,500 resulting in a final county cost of $452,000; and an awarding resolution to Earthworks Land Improvement and Development Corporation for drainage improvements to Army Trail Road with an estimated county cost of $435,376.10 (DTR 0021‑25).
Finance and personnel items approved included acceptance and appropriation of additional funding for the ILD CEO Community Services Block Grant (FIR0111‑25) increasing an account from $1,269,609 to $1,401,491 (an increase of $131,882); approval of employee compensation and job reclassification adjustments for workforce development (FIR0113‑25); and authorization of a contract with International Union of Operating Engineers Local 150 for public works stormwater and facilities management (FIR0115‑25). Those motions were moved by Vice Chair Cahill and seconded by other members and carried by voice vote.
The meeting record shows unanimous voice approvals for the listed items where vote tallies were not recorded individually. No motions listed in the meeting excerpt failed; all named motions carried. Where questions arose about contract timing or funding source, staff from procurement and finance provided explanations during the meeting prior to each voice vote.
Votes at a glance (selected items from the meeting): - HSP 5‑25 (Garden Works project amendment): increase encumbrance $4,992; amended contract not to exceed $74,992 — approved. - HSP 8‑25 (Outreach Community Services Inc. amendment): increase encumbrance $15,000 — approved. - HSP 28‑25, HSP 29‑25, HSP 30‑25, HSP 31‑25 (weatherization contracts): approved (individual caps as reported above). - Rescind requisition 25‑11‑86 and award to Airway Systems (F&P 33‑25): $37,525 — approved. - FMCO 1‑25 (AP Grease Trappers Inc. change order): increase to $102,750 — approved; subsequent limited extension to Aug. 31, 2025 — approved. - F&P 34‑25 (Fox Valley Fire and Safety renewal): $117,250 — approved. - FWP 17‑25 (water tank rehab): $390,600 — approved. - FWP 18‑25 (Mid America Waters): $62,500 — approved. - PWP 19‑25 (Riviera Electric Supply Company): $7,072,090 — approved. - TEP 9‑25 (Cara Company Inc. GPS core‑site management): $39,500 — approved. - Transportation intergovernmental (Darien retaining wall amendment): county increase $264,500; final county cost $452,000 — approved. - DTR 0021‑25 (Earthworks — Army Trail drainage): estimated county cost $435,376.10 — approved. - FIR0111‑25, FIR0113‑25, FIR0115‑25 (finance/resolution items): accepted/approved.
No roll‑call tallies were provided in the transcript excerpt; the minutes record voice votes with motions carried. Where staff clarification was requested (for example, on contract start dates or the proper use of special funds), procurement and finance staff provided answers on the record.
The board adjourned after the presentations and budget discussions that followed.