Brownfields update: Green Bay reports progress on EPA assessment and cleanup grants

5342868 · July 10, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Brownfields program staff reported progress on three EPA grants — assessment, cleanup and revolving loan fund — noting 13 assessment projects under way, an anticipated start to demolition and remediation at Badger Sheet Metal site, and an upcoming EPA grant round the city plans to pursue.

Brownfields program staff provided a quarterly update on June 17, describing activity under the city’s three EPA grants: a community assessment grant, a cleanup grant for the Badger Sheet Metal site and a brownfields revolving loan fund.

Staff reported the EPA community assessment grant ($500,000) has supported 13 assessments along the Fox and East River corridors and other locations; about 69% of that grant had been expended at the time of the update and staff said they will seek a new assessment grant when the next EPA round opens because remaining funds will not cover all planned work. The cleanup grant (approximately $1,000,000) will support demolition and remediation at the Badger Sheet Metal site; staff anticipate demolition and remediation work to begin in the coming weeks and noted a public comment period for the cleanup alternative is open.

The revolving loan fund ($800,000 award) has not yet issued loans but staff said they expect the fund to support developers’ cleanup costs for the Badger Sheet Metal redevelopment. Staff also provided a project list and expense detail in meeting materials and noted Brownfields conference attendance and upcoming technical assistance activities.

Why this matters Staff said the assessment grant work seals the pipeline for future redevelopment by identifying environmental conditions and bringing sites to shovel‑ready status. The Badger Sheet Metal remediation is a prerequisite for eventual redevelopment of the shipyard/Broadway corridor parcels and is tied to the previously discussed ground lease option that allows a developer to proceed with site control while the city retains title until EPA closeout.

Quote from meeting Brownfields staff: “We anticipate demolition, excavation and remedial activities to start here at the end of the month.”

Next steps Staff said they will continue to submit invoices for assessment work, pursue another EPA assessment grant when available, proceed with the cleanup public comment process and expect to use revolving loan funds to support developer cleanup activity where eligible.