County staff seek $1.2 million amendment for county building repairs and ceiling upgrade
Summary
Staff asked the board to approve an amended contract (approximately $1.205 million) to cover additional work on the county administrative building, including wall bracing to current code and lobby renovations; staff said the work would be executed through an amendment with DES.
Get email alerts on the Facilities Maintenance topic
No spam. Unsubscribe anytime.
Cowlitz County staff told commissioners they need authority to execute a contract amendment to expand the scope of an administrative building repair and interior upgrade project to about $1.2 million.
The project scope includes scaffold rental, an envelope specialist, engineering and an observation evaluation of the whole building, with immediate focus on repairs to the south-facing section where water intrusion behind the stonework is causing detachment. Staff said the increase reflects additional items identified during further investigation and the inclusion of a lobby redo.
“Pretty much, what I'm asking for today is the authority to give an approval for this amount, and it's to execute the contract amendment with DES,” a staff member told the commissioners. The staff member characterized the figure as a guaranteed maximum price increase from about $1.1 million to roughly $1.2 million, and said the amendment would include reinforcing walls and bracing to meet current code.
Staff described the proposed action as an amendment rather than a change order because work had not yet started; staff said any additional change orders would still require board authority. Board members present indicated assent in the public discussion.
Why it matters: the amendment would address building safety (wall bracing to current code) and public-facing lobby upgrades, and will affect county capital spending and contract administration.
Details and next steps: staff said they would provide the board a copy of the amended agreement and a full accounting of total project costs. Staff also said they had requested an engineer’s estimate and would continue to review line items to keep costs reasonable and transparent.