District 58 reports middle‑school additions on schedule; phase‑2 elementary work advancing

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Superintendent and facilities staff updated the board on summer construction: middle‑school demolition about 50% complete, phase‑2 elementary demolition about 90% complete, ComEd electrical work remains a scheduling risk.

District officials updated the board June 9 on summer construction and renovation work tied to the district’s capital program.

Superintendent Dr. Russell and facilities staff (Kevin Barto and Jeff Newstead) reported that middle school addition work is on schedule with demolition approximately 50% complete and mechanical/electrical/plumbing work ramping up. Phase‑2 elementary demolition was described as roughly 90% complete with MEP rough‑in, roofing and masonry work underway.

Why it matters: The work affects summer logistics, punch‑list items and warranty follow‑ups and the district cautioned that utility work remains a critical path item. Officials said ComEd has committed to completing remaining service work at Herrick by the end of June but that late storms could delay utility crews and slow construction.

Other notes: Phase‑1 elementary punch‑list and warranty items remain active, including window installation at Puffer and gym work at Highland. Custodial teams are performing deep summer cleaning in non‑construction buildings. The district thanked custodial and maintenance teams and said packaging and moves out of renovated areas went smoothly.

Next steps: The district will monitor ComEd schedules closely and continue contractor coordination; work on punch‑list and warranty items will extend into the summer. The facilities team will keep the board informed about any schedule impacts.

Ending: Officials emphasized ongoing coordination between the district, contractors and the village; they asked for continued patience from staff and families as work progresses.