Selma rejects lone bid for downtown string-lights; council directs value-engineering and rebid
5133511 · July 2, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.
Summary
After a single contractor bid $503,000 for High Street string-lighting—well above the city engineer's $184,800 estimate—council rejected the bid and directed staff to redesign the project to reduce cost and rebid, favoring sidewalk-mounted lights instead of long cross-street spans.
The Selma City Council on July 1 rejected a lone bid for a downtown High Street string-lighting project and directed staff to value-engineer the design and rebid.
Only one contractor submitted a base bid of $503,000; staff said…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans