Detention center HVAC replacement delayed; commissioners approve time‑only change order
Summary
Sweetwater County commissioners granted a time extension for the detention center rooftop unit and air handler replacement project after long component lead times delayed completion. Substantial completion was extended to Nov. 14 and final completion to Dec. 15, 2025.
Get email alerts on the Facilities Maintenance topic
No spam. Unsubscribe anytime.
The Sweetwater County Board of County Commissioners approved a time‑only change order July 1 that extends the Sweetwater County Detention Center rooftop unit (RTU) and air‑handler replacement project because of long equipment lead times.
Public Works Director Jean Legurski reported the RTUs and curbs required for rooftop installation experienced substantial procurement delays. “We ordered these back in February. They were supposed to be in in 2 to 3 months. We've gotten them in 5,” Legurski said. Air‑handling units still lacked confirmed delivery dates, she added.
Nut graf: Because component deliveries were outside contractor control, the board approved a contract time extension to avoid penalizing the contractor for supply‑chain delays.
The change order resets the contract’s substantial completion from June 27, 2025, to Nov. 14, 2025, and the final completion date from July 25, 2025, to Dec. 15, 2025. Commissioners voted in favor; Commissioner Jones stepped in to lead the item while Commissioner Richards recused himself for a reported conflict of interest related to employment.
Ending: The board approved the time extension without adjusting contract price; staff will monitor progress and return to the board if additional schedule or cost changes are required.