Wyoming DOT outlines repairs and safety upgrades for Green River tunnels; westbound lane goal set for Oct. 31

5123897 · July 2, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Wyoming Department of Transportation officials detailed damage assessment and a phased repair plan for the I‑80 Green River tunnels after a multi‑vehicle fire and collision on Feb. 14, 2025. DOT aims to reopen the westbound tunnel to traffic by Oct. 31 and pursue further intelligence and fire‑suppression upgrades next year.

Wyoming Department of Transportation district engineer John Eddins told the Sweetwater County Board of County Commissioners on July 1 that crews have assessed tunnel damage from the Feb. 14, 2025 crash and are advertising a repair contract that aims to return traffic to the westbound tunnel by Oct. 31, 2025.

Eddins said the incident involved 26 vehicles and three fatalities and required an immediate traffic detour onto Flaming Gorge Way (I‑80 Business). “We were able to get concrete barrier set, headlights screening on top of the barrier, and we put 2 lane, 2 way traffic in the eastbound tunnel on I‑80,” he said. He described recurring problems with barrier alignment and a damaged crossover that required repair.

DOT hired Clean Harbors on an emergency basis to remove burned…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans