Carmel approves multiple utilities easements and change orders, including well drilling and wastewater warranty adjustment

5123133 · July 2, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved change orders and easements July 2 for water and wastewater projects, including an added cost to deepen a new well, final change order deduct for a wastewater digester warranty, and permanent and temporary easements on North Michigan Road.

The City of Carmel Board of Public Works and Safety approved several utility-related items July 2, covering well construction, wastewater project changes and water-line easements.

Lane Young of Utilities explained a change order with National Water Services LLC for $13,730 related to a new well project. The drill depth extended about 10 additional feet, and Young said the change order covers the extra materials and labor. “We have got a project where we're building a new well, near one of our other well sites, and the depth that they needed to drill ended up going another 10 feet,” Young said.

The board approved a change order for the wastewater plant digester gas piping replacement project with American Structure Point Inc. as a deductive change. Young said the contractor had originally included a five-year warranty in the contract price; the city elected to purchase the warranty directly from the equipment manufacturer, so the contractor deducted the warranty cost from the contract amount.

The board also approved water-line easement agreements for a Michigan Road project, including a temporary easement and a permanent easement to allow the city to take service areas off legacy Citizens Energy mains. Young said some customers remain on Citizens Energy mains; completing the project will transfer those customers to city service.

Each item was moved, seconded and approved by the board. Several of the easements and a pair of county variance agreements for water-main depth were described as previously approved by the county and were submitted for signature after the county updated its forms.