Greenwood Pool demolition cleared after bid protest; awarded bidder ABW to begin demolition in fall
Summary
City staff said a bid was initially misdelivered, then accepted and awarded to the lowest bidder (Associate Building Records/ABW) after a protest decision on May 23; demolition above-grade is scheduled tentatively for Sept. 26–Oct. 7, with staff coordinating pool closures and sign requirements tied to CDBG rules.
City staff told the Economic and Community Development Committee that a bid protest delayed Greenwood Pool work until a hearing officer’s May 23 decision cleared the award to the lowest bidder, identified in committee materials as Associate Building Records (ABW).
Director Stevens explained that one bid had been “improperly delivered” and was opened the following day at the engineers’ recommendation; that overlooked bid…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat