Board approves concrete replacement and new ADA path at Garish campus
Summary
The board approved Royal Cement’s estimate and contingency not to exceed $136,419 to replace building sidewalks, add ADA‑compliant access to athletic bleachers and install a concrete path from the Garish campus to the neighborhood.
Get email alerts on the Facilities Sitework topic
No spam. Unsubscribe anytime.
The Southgate Community School District Board of Education on June 24 approved concrete replacement work at Garish school and associated site improvements, including a new ADA‑compliant concrete path to the adjacent neighborhood, athletic pad and dugout work, and sidewalk replacement around the building.
A staff member described multiple problem areas flagged during a site inspection and recommended Royal Cement under an existing five‑year district contract for concrete work. The staff presentation explained the scope includes: replacing building sidewalks and damaged sections of district‑responsible city walks adjacent to district property, adding concrete pads under softball bleachers and dugouts, installing a concrete sidewalk to bleacher areas that currently lack ADA access, and replacing a deteriorated asphalt path from the site into the neighborhood.
Staff cited longevity and base‑condition concerns as reasons to choose concrete over continuing asphalt repairs. The staff estimate put new concrete for baseball and softball at $57,552 and building sidewalk replacement at $58,008.66; staff asked for a contingency of $20,000 and recommended board approval of Royal Cement’s estimate and contingency for a total not to exceed $136,419.
Board members asked whether the city was responsible for sidewalk repairs that abut district property. Staff said the district follows the standard practice of removing and replacing flags where the walk touches district property and that the district has to maintain these walks, including snow removal, because they are contiguous with district grounds.
The board approved the authorization to Royal Cement by voice vote.
Ending: Staff will coordinate work and ensure ADA standards for slopes and crosswalks are met; the project will proceed under the district’s existing five‑year contract with Royal Cement.