Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Rail And Road Closure topic
No spam. Unsubscribe anytime.
County, FDOT and CSX detail 8‑day full closure at Northlake/Beeline; town urges three weeks' notice and emergency access plan
Summary
County and FDOT engineers, CSX representatives and local safety agencies told the Loxahatchee Groves Town Council on July 1 that CSX will require a full closure of the Northlake/Beeline crossing for a rail replacement expected to last eight days, and described traffic detours, emergency-access arrangements and communications plans.
Get email alerts on the Rail And Road Closure topic
No spam. Unsubscribe anytime.
Mary McNicholas, the town’s government‑relations representative, told the Town Council on July 1 that the town has been coordinating with county, state and CSX officials after learning the railroad crossing work would require a full closure.
County and FDOT project staff said the closure will remove the crossing and rebuild it, that CSX is targeting an eight‑day window, and that officials expect to provide at least three weeks' public notice before the closure.
That notice matter: “We will have at least 3 weeks notice,” McNicholas said. She and other town staff described the town’s written maintenance‑of‑traffic plan and said the goal is to protect residents’ north‑south access through the community during the closure.
Why it matters: the crossing at Northlake Boulevard and Beeline Highway sits on a widening project FDOT is already building. FDOT and CSX said they must remove the rail panels, replace the track bed and ballast and then rebuild the vehicular panels — work CSX says will take a continuous, day‑and‑night effort for about eight days.
What officials told the council
Mel Pollock, senior project engineer with the Accordena Group, said FDOT’s Beeline Highway project will widen the facility to six lanes and replace the Turnpike bridge approaches; CSX approached FDOT after the roadway work to coordinate a full crossing replacement. “This will be a full closure of East and West North Lake. CSX is pretty adamant that this will be an eight‑day closure,” Pollock said.
Pollock and Palm Beach County engineer David Ricks said the team has worked through temporary signal changes, removal of an overhead signal truss so traffic shifts can occur, and a plan to keep one ramp available for emergency vehicles under law‑enforcement control. Pollock said CSX has agreed that the ramp from southeast Beeline to westbound Northlake will be maintained for emergency use 24/7 under PBSO direction during the closure.
Ricks described the traffic monitoring and response approach county staff will use: signal modems on key intersections so timing can be adjusted remotely, “flicker” devices deputies can deploy, drones for real‑time surveillance, and cameras on key signals. He said Palm Beach County plans mailers to affected ZIP codes after the closure date is set and that Palm Beach County traffic operations will install and monitor portable message signs and adjust signal timing on detour corridors.
Public safety and emergency access
Lieutenant Darla Sowers, Palm Beach County Sheriff’s Office, said PBSO will assign patrol, motor units and community officers to traffic duties and will use drones and on‑the‑ground ‘flicker’ control to create gaps when needed. Palm Beach County Fire Rescue Chief Amanda Vamero said the agency is “resource rich” and can surge staffing or use air assets if needed. “If we need to utilize the TraumaHawk to land and get a critical patient out faster because of traffic, we have that ability,” Vamero said.
Communications and timing
County staff told the council that the county and FDOT will push information through a project website and social media, place 35–40 portable changeable message signs at key intersections, and run paid social and billboard messaging once a firm CSX start date is announced. John Carter, chief of staff to Vice Mayor Sarah Baxter (representing the vice mayor’s office), said the county will use Every Door Direct Mail; staff described an outreach plan covering roughly 50,000 deliveries across likely affected ZIP codes once CSX confirms the date.
Detours and traveler guidance
Planners said two primary detour corridors have been identified for the full closure; county traffic staff will prioritize the primary detour corridors (including Okeechobee and Southern corridor routings) and adjust signals to increase throughput. Staff warned that while detours will move the majority of through traffic, local drivers accustomed to shortcuts will pressure local roads and that PBSO will prioritize preventing unsafe shoulder‑driving and shortcutting.
Next steps
Officials said CSX is to provide the town its next scheduling update by July 3. Pollock said the team was targeting the “fourth Friday in July” as the possible start for the closure but that CSX has not given a firm date; council and staff emphasized they would not start public outreach until the county and CSX set a date and the town receives the promised three weeks' notice.
Community impact and caveats
Town staff and safety officials repeatedly stressed that the town does not control whether CSX executes the work but is coordinating to preserve emergency access and to limit traffic impacts. Officials acknowledged the closure will create delays and asked residents to “pack your patience,” as Lieutenant Sowers put it.
Ending
Council members directed staff to continue daily coordination with FDOT, Palm Beach County, CSX and safety agencies, to finalize the town’s communications products once the three‑week window begins, and to prioritize maintaining continuous emergency access under law‑enforcement control during the closure.

