Summary

The board approved multiple procurement awards, including a $1.018M purchase of student and teacher devices, $555,687 for classroom interactive displays, and a $144,468 band uniform order among other equipment funded largely from bond and REMC schedules.

The Anchor Bay School District Board of Education approved a slate of procurement awards on May 28 covering classroom technology, band uniforms and athletic and classroom equipment.

District staff recommended and the board approved a $1,018,203.94 award to People Driven Technologies for student devices (a mix of 340 laptops and 510 Chromebooks) and teacher computer refresh units for the high school, McCance and Great Oaks. The administration said the devices were purchased off the state REMC schedule and are intended to ensure every high-school classroom has district-issued devices for in-class use.

The board also approved a $555,687 contract with Inicomp Technical Services Group for interactive classroom displays (base bid plus teacher stations). Administration said four mobile displays will serve media centers and specified rooms and most classrooms will receive permanently mounted interactive panels. District staff said the vendor was the lowest responsive bidder and that the review team considered long-term cost models and contractor capabilities.

In additional awards, the board approved $144,468.52 for new band uniforms (order reserved pending board approval), $110,587 for high‑school weight‑room equipment, $49,972.80 for 290 teacher task chairs, $43,000 for the Middle School South gym floor sanding and refinishing, and $223,656.59 in early-childhood furniture to update preschool spaces. Food-service pizza was awarded to Little Caesars under a separate food-service contract because of student preference and a la carte revenue considerations.

Administrators said many purchases are funded by the 2022 bond, and others were procured through cooperative contracts (REMC or E&I) or state purchasing schedules to ensure competitive pricing. Staff emphasized delivery lead times for some items: band uniforms estimated at 180 days and device deliveries dependent on vendor inventory.