Bond projects: East Carter culinary lab delayed to fall for art room work; West Carter science wing on schedule

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

District staff reported construction progress on bond-funded projects: East Carter High School’s culinary lab nearing completion before fall but the adjacent art-room expansion will finish later in the fall; West Carter High School science wing and girls locker-room work remain on schedule.

Facilities staff briefed the board on bond-funded construction progress on June 3, reporting that work at East Carter High School is partially complete and that components of the project remain on a later timetable, while West Carter High School projects are proceeding on schedule.

At East Carter High School, staff reported the drop ceiling has been installed, lights are being placed, drywall is finished and primed, and an epoxy floor has been installed but is not yet complete. The culinary lab portion is expected to be finished before the beginning of the next school year; an adjacent art-room expansion (which requires removing a wall) will be completed later in the fall.

At West Carter High School, staff reported plumbing work in the girls locker room, removal of risers in the former band room down to soil level followed by concrete replacement, and that terrazzo has been poured in the new science wing and is being ground down as part of finishing. Cabinets are currently being installed in the science wing; project status was described as on schedule.

No vote or action was recorded; this item was reported as an informational bond update.