Parking-lot bid comes in over estimate; district to rebid, central-office renovation and athletic upgrades proceed

5110259 · May 20, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The district said bids for the central office parking-lot project exceeded estimates and will be rebid; central-office interior renovation work has resumed, and athletic upgrades including a stadium scoreboard permit and phased baseball-field work are underway.

Winton Woods City School District officials told the board Monday that bids for a central-office parking-lot renovation came in higher than anticipated and the project will be rebid, delaying work roughly a month.

Jeremy Day, executive director of business affairs, said contractors cited the amount of fill required to level the sloped site as a primary cost driver. The district plans two public notices with a June 11 bid opening and expects the work to take about two months once started. Day said no general fund dollars are being used for the parking-lot project and that the construction season provides time to complete the work before winter.

On other facilities items, Day reported the central-office interior renovation (CO renovation) has resumed with architecture/engineering firm SHP coordinating work. Athletic projects include additional quotes for wind shear/height measurements and a phased overhaul of the baseball field, with grass work scheduled for late fall to reduce summer water needs. Permitting for a scoreboard at the stadium has started with the vendor providing renderings as part of the permit submission.

Board members asked for cost and timing details. Day said the parking-lot rebid schedule will include two newspaper advertisements and a June 11 bid opening; he also said he will circulate scoreboard renderings to the board once available.

Why it matters: The parking lot and central-office renovation affect staff access and administrative operations, while athletic upgrades impact school events and community use. The rebid increases schedule risk but Day said there is sufficient construction season to complete the work.

Board action: This was an informational update; no formal action was taken on the rebid schedule or permits during the meeting.

Ending: Staff will rebid the parking-lot project, continue CO renovation work with SHP, pursue permits for the scoreboard and complete the baseball field in two phases.