Augusta staff propose $13M night‑shift option to finish Broad Street/TIA corridor one year earlier; commissioners send plan to committee
Summary
Engineering presented a plan to add a second (night) shift to accelerate Broad Street/TIA corridor work at an estimated additional cost of about $13 million; commissioners voted to send the funding plan to the engineering services committee for review.
City engineering staff presented a proposal to accelerate the Broad Street/TIA corridor project by adding a second (night) shift that staff said would move the project completion forward by roughly one year. The contractor estimated additional costs of about $13,000,000 to fund the night shift and related mobilization.
Dr. Malik (engineering)…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat