Council authorizes $81,786 change order to repave Blackwater Court after compaction failures
Summary
Council approved a change order and third-party oversight funding to mill and repave Blackwater Court after compaction tests showed substandard results on recent contractor work; funds are to be released from a letter of credit.
Milford City Council authorized a change order totaling $81,786.50 to repair and repave Blackwater Court after independent compaction tests found the original paving did not meet DelDOT compaction requirements.
Public Works Director Will Schafer told council that during July 2023 paving operations the contractor (CJ Paving) did not conduct the required density tests, and subsequent compaction tests — performed over several…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat