Monroe Local advances facilities work: gym infill on schedule, second driveway talks with county and ODOT, commissioning agent and urgent piping repair approved
Summary
Superintendent Buskirk reported the gym infill is ahead of schedule and classrooms should be ready by January 2026; the board authorized a commissioning agreement for the new high school project and approved an urgent repair to chilled‑water and hot piping at the main campus.
Get email alerts on the Facilities Projects topic
No spam. Unsubscribe anytime.
Superintendent Buskirk told the Monroe Local Schools Board on June 23 that the jail gym infill project is progressing and that the district expects to begin using the added classrooms in January 2026, and he reported movement on a long‑sought second driveway after positive responses from the Ohio Department of Transportation.
"We're scheduled to start utilizing those classrooms in January, '26," Buskirk said, describing the gym infill as on schedule and a relief for overcrowding. He added that architectural work on the new high school has advanced to conceptual designs and that design from start to finish is approximately one year, with an objective to break ground in spring after final design steps.
Buskirk said ODOT acknowledged the intersection of state Route 63 and Yankee Road needs improvements but indicated the state would not hold the district responsible for paying for those improvements; that leaves county coordination as the next step. "ODOT was in agreement. So now it is, you know, just the county," Buskirk said. A district meeting with county officials was scheduled to begin design work for the second driveway.
On agenda consent items the board approved a consultant agreement with 4 Seasons to serve as commissioning agent for the high school project; the motion was moved by Mr. Leeds and seconded by Mr. Grant and carried on roll call. The board also approved a resolution of urgent necessity and a contract with Comfort Systems to repair main campus chilled‑water and hot piping after district staff described leaks in the system as needing immediate attention. The urgent repair motion was moved by Mr. Grant and seconded by Mr. Leeds and carried.
The board also authorized replacement and repair of playground fence gates at NES and agreed to seek painting quotes once repairs are complete.
Discussion: Board members and staff stressed coordination with county engineers and ODOT for driveway improvements and said the commissioning agent will help the district evaluate long‑term maintainability of design choices and mechanical systems.
Decisions: Approve commissioning agent agreement (4 Seasons), contract with Comfort Systems for urgent chilled‑water and hot piping repair, and repair/replace NES playground fence gates.
Why it matters: The decisions affect near‑term facility readiness (classroom availability in January 2026), long‑term capital planning for the new high school, and immediate building safety/operational reliability through the piping repair.
What’s next: Staff will continue meetings with county and design teams and will report back on project designs, implementation schedules and any required budget adjustments.