Council approves change order to upsize well motor and pump at Water Plant 2
Summary
After well testing showed lower-than-expected static water elevation, the council approved a $20,500 change order to increase the pump/motor size at Water Plant 2 to restore operating efficiency.
Get email alerts on the Utilities Infrastructure topic
No spam. Unsubscribe anytime.
The Montgomery City Council approved change order number 2 on June 24 to upsize the motor and pump at Water Plant 2.
Staff explained testing at the newly drilled well showed lower static water elevations than predicted by the hydrogeologist’s pre-drilling study. To achieve the planned operating efficiency and reduce long-term wear, staff recommended upgrading from a 60-horsepower pump to a 75-horsepower pump. The change order increases the project cost by $20,500 and adds 14 days for equipment lead time.
Council members asked why the difference was not detected earlier; staff said the site-specific well testing and seasonal water-level variation made the difference apparent only after construction. Staff reported test production rates consistent with expectations and described contingency plans if a pump fails, including rental options to maintain supply.
A motion to approve the change order passed by majority vote. Staff will proceed with procurement and schedule the installation; the project remains on track for the final start-up once the motor and pump are installed and electrical work completed.