The Roswell Mayor and Council committee unanimously authorized a memorandum of agreement June 24 to join four other North Fulton cities in an Atlanta Regional Commission-led update to the North Fulton Comprehensive Transportation Plan.
Get email alerts on the Transportation Planning topic
No spam. Unsubscribe anytime.
The Roswell Mayor and Council committee unanimously authorized the mayor or city administrator to sign a memorandum of agreement June 24 to participate in a 2025 update of the North Fulton Comprehensive Transportation Plan (NFCTP).
Why it matters: ARC is funding a regional NFCTP update with federal assistance; Roswell staff said the update will include a 12–18 month process for procurement, public engagement and final adoption, and the plan will guide multi-jurisdictional transportation projects across North Fulton.
What staff said: Greg Nicholas, interim director of transportation, told the committee that ARC will manage the project and federal contracting in coordination with GDOT and that one staff member from each of the five participating cities will sit on a project management team. Nicholas said the total estimated project cost is in the vicinity of $1.2 million, including federal funds and a required local match shared among the five cities.
Financials and Roswell’s share: Nicholas said the overall assistance package includes $990,000 in federal funds and a local match totaling $247,500 to be shared by the five cities; based on ARC’s 2023 population estimates, Roswell’s share was $58,642. Staff recommended using unprogrammed SPLOST funds to cover Roswell’s contribution.
Action: Councilmember David Johnson moved approval; Councilmember Gee Lee Hills seconded. The committee voted unanimously to authorize the mayor or city administrator to sign the memorandum of agreement and approve the budget amendment for Roswell’s share.
Next steps: With unanimous authorization, ARC will begin consultant procurement following formal authorization by all five cities; staff said procurement and the plan update are expected to take 12–18 months and will include evaluation and public engagement phases.
Limitations and clarifications: Nicholas said the typical CTP is managed at county level but ARC is managing this update because Fulton County is fully incorporated. Johns Creek will serve as the administrative city to collect local match payments; Nicholas said Johns Creek is not receiving an administrative fee for that role.