Board approves right-of-way contract and amendments to 5-year road program to pursue $800,000 bridge grant

5058593 · June 24, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The supervisors authorized the chair to sign a right-of-way contract for a Perrin-area project and approved an amendment to the 2026 county five-year program to pursue a competitive bridge replacement grant worth $800,000 with $200,000 local match.

The Pottawattamie County Board of Supervisors approved a right-of-way contract for project L-2025 Perrin VA 28 Perrin-78 and amended the county’s five-year secondary roads program to include a bridge replacement application that would seek $800,000 in competitive grant funding.

Interim Engineer Brandon Burmeister presented the items. He described the bridge as located on M47 north of Highway 6 and said the county submitted the project for a competitive Highway Bridge Program grant. “It would be $800,000 of grant funding and the other $200,000 of the funding… would be farm-to-market money,” Burmeister said. He added the grant application had met qualifications and would be packaged with roughly 20 other bridge projects for consideration.

Nut graf: The board authorized right-of-way documentation for a named Perrin project and amended its 2026 County Five-Year Program (CFYP) to support an IDOT-administered competitive bridge grant, with the county providing a $200,000 local match from farm-to-market funds if the grant is awarded.

Burmeister noted the bridge’s construction date (1964) and described ongoing deterioration; the board voted by roll call to approve the amendment and the right-of-way contract. The funding source was identified as the competitive highway bridge program administered through IDOT and federal funds.

Ending: The board approved the engineering and program amendments and recorded aye votes from supervisors present; staff said the county would proceed with the grant package submission and follow grant-award procedures if selected.