Board approves $163,322 change order for Castle High School renovation after negotiations

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Trustees approved a negotiated change order totaling $163,322.50 for electrical, domestic water, sanitary and construction installation work on the Castle High School renovation; the original request was $202,514 and $1,005 will be recaptured through the architect contract.

The Warrick County School Corp board on June 23 approved a change order for the Castle High School renovation project, reducing an original request of $202,514 to a negotiated total of $163,322.50.

Dr. Redmond presented the change order and explained it covers four scopes of work — electrical, domestic water, sanitary and construction installation — with the final pricing reached after negotiations between the contractor and the architect. "The original change order request for this work totaled $202,514. Working together, we were able to arrive at a price of $163,322.50, of which an additional $1,005 will be recaptured through the architect architect contract," Dr. Redmond said.

A board member who serves on the construction committee said the committee vetted the figures and reduced the number from a much higher earlier estimate to the current negotiated amount. The motion to approve was made by Missus Wilhelmus and seconded by Mister France; the vote carried by voice.

Board members noted the renovation involves a roughly 50-year-old building and that change orders are common in such projects. No further financial contingencies or schedule impacts beyond the negotiated scope were specified during the discussion.