Commission approves $26,250 change order for Clay County bridge deck repairs

5054352 · June 6, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Clay County Commission approved a change order for additional concrete patching on the Northeast 100 and 40th Street bridge over Clear Creek after new damage was found; the unit price was renegotiated, and the contract increased by $26,250.

The Clay County Commission approved change order No. 1 for Road and Bridge project 25‑1RB108, adding work and cost to the Decker Construction Services contract for deck repairs on the Northeast 100 and 40th Street bridge over Clear Creek.

Road and Bridge Director Tom Degenhardt told the commission the contract’s Portland cement concrete patching quantity must increase from 525 square feet to 1,725 square feet after an additional freeze–thaw cycle caused more deck delamination. Because of the substantial increase in quantity, Decker Construction negotiated a lower unit price, dropping from $51.20 to $30.80 per square foot, producing a net contract increase of $26,250 for the item and overall contract.

The nut graf: The commission voted to approve the change order after the director described the additional deterioration and a negotiated unit‑price reduction; the work is intended to repair deck delamination identified after the original March 2024 evaluation.

Degenhardt said the March 2024 deck evaluation formed the original quantity estimate; subsequent winter freeze–thaw cycles contributed to further concrete delamination. He presented the negotiated unit price and the resulting net change and offered to answer questions; none were raised.

Commissioner Johnson moved to approve resolution 2025.179 to authorize the change order. The roll call recorded Commissioners Johnson, Wagner, Thompson, Carpenter, Whittington and Lawson all voting in favor; the motion passed 6‑0.

Ending: The commission closed the item and proceeded to the regular reports section of the meeting.