Plan Commission approves 5‑story mixed‑use affordable housing at Verona Road interchange amid divided public input

5052949 · June 24, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Madison Plan Commission unanimously approved a conditional use June 23 to allow demolition of two commercial buildings and construction of a five‑story, 93‑unit mixed‑use building with a small commercial/community service space at 4506–4514 Verona Road.

The Madison Plan Commission on June 23 approved a conditional use permit for a five‑story mixed‑use building at 4506–4514 Verona Road, allowing demolition of two commercial buildings and construction of a 93‑unit apartment building with about 324 square feet of leasable commercial/community service space.

Planner Colin Punt of the City of Madison summarized the staff report and an addendum. Punt said the comprehensive plan recommends a “general commercial” future land use for the site and noted that, in the May 19 staff report, staff had identified concerns with conditional‑use standards (particularly standards 1, 2 and 4). After the applicant submitted additional materials and staff published an addendum, Punt said staff believed it “may be possible for the commission to find that standard to be met,” and that staff’s recommendation was approval provided the commission makes findings for the conditional‑use standards. Punt also advised that a motion should state findings and reasoning.

The applicant team (Kenilworth & Bruce Architects and Lincoln Avenue Communities) presented plans showing a U‑shaped building pushed south and west on the site to form a sheltered central courtyard with an outdoor play area and an indoor playroom intended for children, underground and surface parking, and a small dedicated community service / leasable space near the main entry. Architect Kevin Burrow described exterior materials and acoustical design choices, and developer Kevin McDonald said the project had been awarded state housing funds and that the building will pursue high-performance certifications (Enterprise Green Communities Plus, “zero‑energy ready” practices and Energy Star measures). McDonald also listed on‑site supportive-service partners including Lutheran Social Services, Employment and Training Associates and Dane County Veterans Service Office.

Supporters who spoke at the public hearing highlighted the developer’s experience with affordable housing in Madison, the proposal’s unit mix (45 one‑bedrooms, 23 two‑bedrooms and 25 three‑bedrooms), on‑site supportive services and indoor‑air quality measures. Architect/consultant Lindsay Alton (EcoAchievers) described the proposed energy and indoor‑air systems—MERV‑13 filtration and a UV catalyst filtration technology—and said the project is pursuing recognized green and IAQ certifications.

Opponents raised safety and public‑health concerns tied to proximity to the Verona Road/BeltLine interchange. Public commenters and an advocate cited research on near‑roadway air pollution and said a development sited within a few hundred feet of a heavily trafficked interchange raises respiratory and long‑term health risks for residents. One opponent urged commissioners to “Just say no to this proposal,” saying near‑road pollution “increases the risk of asthma in children” and other serious health outcomes; another commenter, a neighborhood resident, described concerns about pedestrian crossings and asked for an updated traffic study.

Attorney and public commenter Robert Proctor (speaking in support) argued the commission must apply the conditional‑use standards based on substantial evidence and that the record—including the applicant’s traffic and safety data, staff addendum and supportive letters—did not contain substantial evidence to deny the permit. The city’s assistant attorney later clarified statutory context for the commission: a conditional use permit under state law “does not need to be consistent with the comprehensive plan,” but the decision to approve or deny must be supported by substantial evidence; local ordinance language and the commission’s standard‑by‑standard findings remain relevant to that review.

Commission discussion covered pedestrian access, transit and park proximity, unit mix and supportive services, the proposed children’s play areas, noise and acoustic mitigation, and whether the site’s “general commercial” future‑land‑use designation weighs against residential use. The developers committed to a striped crosswalk on the frontage road if required by traffic engineering and confirmed the child play area and a full‑size community room will be included, with property management coordinating hours and access.

After extended discussion, Alder Reguera moved to approve the conditional use, finding standards 1, 2, 4 and 8 satisfied based on the supplemental materials and staff addendum; Commissioner Heck seconded. The chair called for objection to unanimous approval; no objection was raised and the commission recorded the motion as approved unanimously. The action is advisory for conditional uses per the plan‑commission process and will be reflected in the formal permit and zoning records.

Why it matters: The site is at a major highway interchange and carries typical questions about compatibility of residential uses adjacent to high‑traffic corridors. The commission balanced those location‑based concerns with evidence the applicant provided about transit and pedestrian access, indoor air‑quality measures, and availability of supportive services and family‑sized units.

What’s next: Staff will finalize the conditional‑use findings and the permit record; building permits, demolition approvals and any required traffic or crosswalk improvements will follow standard city review and permitting processes.

Direct quotes (selected): "Staff recommend that the commission approve, the conditional use request," said Colin Punt, planning staff. Kevin McDonald, development partner, said the building will be high‑performance: "This will be our first net 0, ready certified building with renewable energy, indoor air quality certifications, and a UV catalyst filtration system." An opponent told the commission: "Just say no to this proposal."