District begins design for major North High mechanical upgrade; chiller at West to be replaced

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Facilities staff recommended on-call engineering services and the start of design for a large mechanical, electrical and plumbing project at North High School — possibly up to $12 million over multiple years — and approved replacement of one failed chiller at Lee’s Summit West.

Lee's Summit R-VII facilities staff told the finance committee June 23 they will begin design work and early procurement on major mechanical and life-safety system upgrades as part of the 2025 bond work.

Mister Gorrell said the district is engaging Henderson Engineers for mechanical, electrical and plumbing design on a large North High School project that could reach $12 million and likely take multiple years to complete. The project would replace original systems and could include HVAC, intercom and fire-alarm work; staff said some equipment will be long-lead and require early orders.

The nut graf: The committee approved contracting design services now so that the district can begin long-lead procurement and staged construction next summer; staff emphasized the building’s age and inefficiencies as the impetus for early work.

Gorrell said North High is largely all-electric heat and that transitioning to gas heating and other system replacements would likely yield long-term energy savings. "We would really like to transition this over to gas heat and realize some long term energy savings in the building," he said.

Separately, the committee reviewed a recommended purchase to replace a dead chiller at Lee’s Summit West. Facilities staff said West currently has three large chillers, two of which are original to the building; they expect to start the school year with two functioning chillers and have ordered a replacement for the nonworking unit.

Staff said both projects were already scored and prioritized on a multi-year maintenance plan and noted the North High work will proceed through preconstruction, scoping and staged construction to manage timelines and budgets.

Ending: Staff will proceed with design and early procurement for North High mechanical systems and advance the chiller replacement contract for Lee’s Summit West; both items will return for board approval as required by procurement policy.