Public Service says it will file confidential large‑load contracts, but won’t precommit interim tariff
Jun 20, 2025
Public Service Company told the Colorado Public Utilities Commission on June 20 that it will provide the commission with electric service and interconnection agreements for strategic economic development and other large‑load customers above 100 megawatts on a restricted, highly confidential basis while the company works toward a dedicated large‑load tariff.
The full story
Public Service Company told the Colorado Public Utilities Commission on June 20 that it will provide the commission with electric service agreements (ESAs) and interconnection agreements (ISAs) for strategic economic development and other large‑load customers above 100 megawatts on a restricted, highly confidential basis while the company works toward a dedicated large‑load tariff.
The company’s witness, Mr. Bailey, said the utility is “willing to do that” when asked whether it would file those agreements in this docket or a miscellaneous proceeding, and that model versions of updated ESAs and ISAs will be filed “with its statement of position.”
Why it matters: parties and commissioners pressed Public Service for a mechanism to ensure the commission is informed about large‑load deals made before a formal large‑load tariff is in place. Company witnesses repeatedly told the panel they will engage stakeholders on tariff design but will not precommit to including the interim principles described in rebuttal testimony in the final tariff.
Most of the hearing record focused on how the company would treat large customers during the interim period before a new tariff’s effective date. Bailey told counsel that any customer who first takes service after the large‑load tariff’s effective date would be subject to that tariff, while “current customers and customers who begin to take service during the interim period would not automatically move into that large load tariff.”
The company also described the internal “step” or probability framework it used in testimony to prioritize generation procurement during the interim phase. Bailey confirmed that the company currently uses the large‑load principles in ongoing negotiations and that its framework treats a 90% probability (the ninth step in the staged process) as the threshold to trigger moving generation projects from an “incremental need pool.” He added, “We have an obligation to serve them as soon as we are able,” and said delay could push prospective customers “out of our state and out of our market.”
The utility agreed to replace explicit percentage probabilities with a stepped labeling (step 1 through step 10) in its materials and said it would file restricted, highly confidential versions of ESAs and ISAs and updated model contracts as part of its statement of position.
What remains open: company witnesses declined to take on some risk questions—when asked if the company would accept the risk of building generation that might never be needed, Bailey said he was not authorized to speak to that and identified other witnesses who could. Commissioners and intervenors also sought clearer commitments about whether strategic economic development customers beyond the five identified in a confidential exhibit could be added to trigger incremental procurement; Bailey answered that Public Service “would not.”
Ending: The company and counsel agreed to continue stakeholder engagement on tariff development and to provide confidential agreement templates to the commission while the larger stakeholder and tariff process continues.
Written with AI from the event video and transcript. Check it against the source ↓
