Samuels Group, contractors report foundation work under way; Page County turbine deliveries expected mid‑July

4979237 · June 18, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Contractor and construction updates at the Page County meeting covered progress on a county building project and an update on an associated turbine delivery schedule.

Contractor and construction updates at the Page County meeting covered progress on a county building project and an update on an associated turbine delivery schedule.

Brian with Samuels Group told the board crews were laying out and digging footings, with concrete pours and testing scheduled, and that masonry subcontractors expected to begin laying block below grade the following week. Northwest Steel brought a jobsite trailer and was preparing a bracing plan for precast walls; electricians and plumbers are scheduled to return when foundation block work begins.

Separately, a contractor identified as John reported that turbine deliveries in Page County are expected to begin in mid‑July and that the county has started digging foundations and pouring first lifts of concrete for turbine foundations. John clarified the water used for dust control is coming from a private well; he said an electrical contractor (JFE) has a separate contract with the city of Coyne to obtain water for electrical bores, not for general dust control.

John also said the FAA had advanced a permit for the site’s emergency generator to “final evaluation status” and that the county is ordering the generator early because of long lead times so the equipment will be available when foundations and concrete bases are ready.

Why it matters: Foundation and delivery timing affects the construction schedule, crane mobilization and potential traffic disruptions. The water‑use clarification addresses resident questions about source and permitting for construction water.

Details from the meeting: Samuels Group reported use of rough‑terrain cranes for rebar and foundations and the potential arrival of larger cranes in mid‑July to set turbines. Contractors described plans to begin precast setting once the interior block walls and backfilling are ready. The preferred vendor for truck body equipment is located in Des Moines for the separate highway equipment procurement.

What’s next: Contractors will continue foundation work and coordinate delivery dates; project managers expect turbine deliveries beginning in mid‑July and will advise the board if schedule changes occur. Staff said they will verify specifics about dust control near residences and follow up with the board.