Phenix City authorizes emergency replacement of Village Springs sanitary sewer main at estimated $103,356

4138438 · June 18, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved a resolution to replace about 180 feet of sanitary sewer main at Village Springs and to repair a stone pipe, based on a contractor estimate not to exceed $103,356.

Phenix City council members authorized an emergency contract to replace approximately 180 feet of sanitary sewer main at Village Springs and to repair an adjacent stone pipe, based on an initial estimate from Mortarbrating Contractor Inc not to exceed $103,356.

The resolution in the transcript declares the Village Springs Sanitary Sewer Main Replacement an emergency and records approval and adoption on Dec. 31, 2024, with ratification in January 2025. Council asked for a verbal roll-call vote; the transcript shows Council member Bailey, Council member Gordon and the mayor voting “yes.”

City staff described the work as necessary to repair the sanitary main and a failing stone pipe at the location, and they presented Mortarbrating Contractor Inc’s initial estimate to perform the replacement and repair work.

The resolution directs the mayor and city manager to execute the emergency contract up to the stated amount. The transcript does not record contract start dates, specific work schedule, or required permits.

Council discussion focused on restoring sewer capacity in that northern area and ensuring public safety; the transcript does not show any amendments to the contractor estimate or additional funding sources specified during the item.