Hot Springs approves $3.7 million-plus in wastewater contracts tied to ADEQ consent order
Summary
The Hot Springs Board approved multiple contract awards for the Spring Street gravity sewer project, a 54-inch outfall to Lake Catherine, and a sanitary sewer evaluation study, funded by 2025 wastewater bonds and tied to an ADEQ consent administrative order.
The Hot Springs Board of Directors on June 17 approved several contract awards for wastewater system upgrades tied to Arkansas Department of Environmental Quality requirements and the city’s 2025 wastewater bond program.
The board awarded Schedule 1 of the Spring Street gravity sewer project to Boyles Construction for $3,155,462.70 (Resolution R-25-125) and approved Schedule 2 and 3 awards to Diamond Construction with combined totals that bring the larger Spring Street work to a multi-million-dollar program (Resolution R-25-126). The projects are part of ADEQ’s Consent Administrative Order CAO LIS22-077, city staff said.
“Staff recommends awarding the bid received on May 12 to Boyle's Construction ... for schedule 1 of the Spring Street gravity sewer project ... in the amount of $3,155,462.70,” engineering project staff reported. Joey Stadler,…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat