Planning board hears DPW plan to move fleet maintenance to Cogswell site; traffic and stormwater concerns raised
Summary
The Planning Board continued the public hearing on the Cogswell (RTS) expansion for DPW fleet maintenance, where applicants said the project would add about 32 daily trips and that routes used by larger vehicles would continue to favor a longer, less-congested path; neighbors asked for restrictions and mitigation on timing, access, and lighting.
Get email alerts on the Cogswell Fleet Maintenance topic
No spam. Unsubscribe anytime.
The Planning Board continued a public hearing June 17 on a proposal to expand vehicle maintenance operations at the Cogswell site (RTS), including a new fleet-maintenance garage and changes to site circulation and access.
Project representatives told the board the expected net increase in daily trips to the site tied to fleet maintenance would be modest. “In our estimate we came up with 32 trips generated a day from the facility,” a traffic consultant said; the consultant described that figure as conservative and noted some repairs currently originate from the RTS and would shift location but not add comparable townwide vehicle trips. Planning staff and DPW representatives explained that larger DPW vehicles already use a longer, less-congested route through South Street and Central rather than the narrow Mark Tree Road; DPW said supervisors prefer the longer route for heavy equipment.
Neighbors and public speakers pressed the board on cumulative impacts along Central Avenue, noting other proposed and planned projects in the corridor (a daycare, proposed pickleball courts and fields, and other town uses). “There is a traffic issue here,” Holly Clark, a nearby resident and town meeting member, said. Clark recommended the board require conditions limiting truck movements during peak hours and closer study of impacts at the Charles River/ Central Avenue intersection, which she said previously operated at a failing level of service.
DPW staff responded that emergency and snow/ice operations require flexibility: “Limiting the hours that we have access to the facility... could be problematic for our ability to actually triage and repair equipment,” a DPW representative said, noting emergency repairs, night and early-morning work and snow responses occur outside standard business hours.
Stormwater and noise were discussed. Project engineers said they plan to design on-site stormwater management to retain and infiltrate approximately one inch of rainfall, and that the proposed new building will be air-conditioned (closing doors that are currently open at the existing facility) and will include noise attenuation measures such as a sound wall and generator mitigation. The board acknowledged the project will require further technical review and asked staff to confirm stormwater calculations and operational conditions in the draft decision.
The board opened for public comment and heard residents request pedestrian safety improvements at nearby intersections and possible time-of-day restrictions for non-emergency truck movement; the board closed the hearing at the meeting and will prepare conditions in the order for a future decision.
No final permit was issued June 17; the hearing continued with the board asking for additional technical clarifications and proposed enforceable conditions on operations and access.