Council approves small change order, extends timeline for dam reconstruction
Summary
Council approved Change Order No. 7 to the North Terrace/North Ferris Street / Lake Comas Dam reconstruction contract, adding $1,650 and 106 construction days to the contract.
Get email alerts on the Public Works topic
No spam. Unsubscribe anytime.
The Delavan Common Council approved Change Order No. 7 to the Lake Comas Dam reconstruction contract, adding $1,650 and 106 additional working days to the project.
The motion as reported in the meeting referenced the contract for the North Terrace Street/Lake Comas Dam reconstruction and named differing contractors in the transcript; it authorized the additional funds and time. The motion was seconded and passed by the council.
Because the meeting transcript includes inconsistent references to contractor and street names (the audio mentions both Lunda Construction Company and other spellings), staff should confirm the official change-order document for exact contractor names, scope and schedule adjustments.